AI Data Center Power Tracker
The race to build AI is now a race for electricity. This tracker lists the largest AI data centers by the power their computers can draw today and the power they are being built to reach, using independent estimates from Epoch AI.
The largest AI data centers by power
| Site | Location | Status | IT power now | Planned IT power |
|---|---|---|---|---|
| Anthropic-Amazon New Carlisle Amazon, for Anthropic | New Carlisle, Indiana | Operating | 1,037 MW | 1,925 MW (2028) |
| xAI Colossus 2 xAI | Memphis area, Tennessee | Operating | 946 MW | 1,531 MW (2027) |
| OpenAI Stargate Abilene OpenAI, Oracle, Crusoe | Abilene, Texas | Operating | 824 MW | — |
| Microsoft Fairwater Atlanta Microsoft | Atlanta, Georgia | Operating | 636 MW | — |
| DayOne Nusajaya DayOne | Johor, Malaysia | Operating | 473 MW | — |
| Microsoft Fairwater Wisconsin Microsoft | Mount Pleasant, Wisconsin | Building | — | 2,263 MW (2028) |
| OpenAI Stargate New Mexico OpenAI, Oracle | Doña Ana County, New Mexico | Building | — | 1,750 MW (2028) |
| Meta Hyperion Meta | Richland Parish, Louisiana | Building | — | 1,632 MW (2028) |
Running nowPlanned
Source: Epoch AI, Largest AI data centers ranked by power capacity, updated Nov. 6, 2026. Figures are IT power estimates. Tap a column heading to sort.
Stargate, site by site
OpenAI’s Stargate program spreads across seven announced U.S. sites. Only Abilene was running as of Epoch’s April 2026 review. These figures are estimated total facility power, so they run higher than the IT power figures above.
| Site | Builder and hardware owner | Planned power | Running (Apr. 2026) | Status |
|---|---|---|---|---|
| Abilene, Texas | Crusoe; Oracle owns hardware | 1.2 GW | 0.3 GW | About four of eight buildings running; finish expected Q4 2026 |
| Shackelford County, Texas | Vantage; Oracle owns hardware | 2 GW | 0 | Construction since Q3 2025; finish expected Q4 2028 |
| Doña Ana County, New Mexico | STACK Infrastructure (Project Jupiter); Oracle owns hardware | 2.2 GW | 0 | Construction since Q4 2025; finish expected Q4 2028 |
| Milam County, Texas | SB Energy (SoftBank); SoftBank owns hardware | 1.2 GW | 0 | Construction since Q3 2025; finish expected Q4 2028 |
| Port Washington, Wisconsin | Vantage (Lighthouse campus); Oracle owns hardware | 1.3 GW | 0 | Construction since Q1 2026; finish expected Q4 2028 |
| Saline Township, Michigan | Related Digital (The Barn); Oracle owns hardware | 1.4 GW | 0 | Construction since Q4 2025; finish expected Q4 2028 |
| Lordstown, Ohio | SoftBank and Foxconn; SoftBank owns hardware | Under 0.3 GW | 0 | Land cleared, no large-scale construction seen; date unknown |
Source: Epoch AI, OpenAI Stargate: where the US sites stand, Apr. 17, 2026. Epoch notes that OpenAI dropped a plan to expand Abilene to 2.1 GW.
How to read these numbers
A megawatt is a rate, not a total. It measures how much power a site can draw at once. A 1,000 MW site running all day uses 24,000 megawatt-hours.
“Planned” is not “powered.” A site can finish its buildings and still wait on substations, transmission lines or turbines. That gap between a building being finished and a building being powered is where many AI timelines slip.
Estimates move. Epoch revises figures as new satellite imagery and filings appear. Check the source links for the latest numbers.
Common questions
What does a megawatt of IT power mean?
IT power is the electricity the computers themselves can draw: the chips, servers and networking gear. The whole facility draws more, because cooling and power conversion use energy too.
Why is power the bottleneck for AI?
Training and running large AI models takes huge clusters of chips that run around the clock. A site can only grow as fast as utilities, transmission lines and on-site generation can deliver electricity, and new grid connections can take years.
Where do these numbers come from?
From Epoch AI, an independent research group that estimates data center capacity from public records and high-resolution satellite imagery. Epoch says about 80% of its estimates fall within a factor of 1.4 of the true value, so treat them as informed estimates, not official figures.
Is this investment advice?
No. BOSSTOX covers AI infrastructure for education only. Nothing on this page is a recommendation to buy or sell anything.
BOSSTOX covers the infrastructure behind AI for education only. It does not give investment advice or execute trades.
Latest stories
View all