Interconnection Queues Explained: Why Power Projects Wait in Line

Before a new power plant or large load can connect to the grid, it joins a study queue. Here is how that process works and why it has grown so long.

Published

on

Battery Storage at AI Sites

Almost every new power plant, battery or large customer that wants to connect to the high-voltage grid has to pass through an interconnection process. Requests are filed, ranked and studied in an order that is commonly called the queue. In recent years, queues across the United States have swelled, and they now sit at the center of debates about how fast the grid can grow.

What the queue is for

Connecting a large generator or load is not like plugging in a lamp. Adding hundreds of megawatts at one point changes how power flows across the whole regional network. It can overload distant lines, create voltage problems or affect how the system behaves during a fault.

Before approving a connection, the grid operator or utility runs engineering studies to find those effects and to identify the upgrades needed to fix them. The queue is simply the organized line of projects waiting for those studies.

Advertisement

How the studies typically work

Details vary by region, but the general pattern is similar:

  • A developer submits a request with a location, size and technology, along with deposits.
  • Engineers run a feasibility or cluster study to see the broad impact on the system.
  • A more detailed system impact study identifies specific required upgrades and estimates their cost.
  • A facilities study designs the actual equipment.
  • The parties sign an interconnection agreement, and construction can begin.

Many regions now study projects in groups, or clusters, rather than one by one. Clustering lets engineers see the combined effect of many projects at once and share upgrade costs among them.

Why the line got so long

Several forces collided. Wind, solar and storage projects are smaller and more numerous than the big plants of the past, so the number of requests multiplied. Filing was relatively cheap, so developers sometimes submitted speculative projects at several locations, knowing most would drop out. When a project withdraws late, the studies for those behind it may need to be redone, which slows everyone.

Meanwhile, the network itself had less spare capacity in many areas, so more projects triggered expensive upgrades. Those large cost estimates caused more withdrawals, and the cycle repeated.

Reforms and what they aim to fix

Federal regulators and regional operators have adopted reforms meant to speed things up. Common themes include higher deposits and readiness requirements to discourage speculative filings, a first-ready first-served approach instead of strict first-come first-served, firm study deadlines and penalties for missing them, and more use of cluster studies.

Advertisement

Whether these changes shorten waits is something to watch in each region’s published queue data rather than assume.

Why it matters for AI infrastructure

Data centers feel the queue in two ways. The power plants they hope to rely on must clear interconnection before they can deliver energy. And the data centers themselves, as very large loads, increasingly face their own study processes with utilities. Load interconnection rules are less standardized than generator rules, and many utilities are revising them as requests multiply.

For anyone tracking the build-out, queue position and study status are often more telling than an announced megawatt figure. A project that has signed an interconnection agreement is in a very different place than one that has only filed a request.

A Plain-Language Walkthrough of One Project’s Journey

To make the process concrete, imagine a developer proposing a mid-sized solar farm paired with batteries in a rural county. A simplified path through the queue might look like this.

  1. Site control and filing. The developer secures land rights, then files an interconnection request with the regional operator, paying the required deposit and providing technical details about the equipment.
  2. Cluster assignment. The request is grouped with other projects filed in the same window. Engineers model them together.
  3. First results. The study shows that the combined cluster would overload a transmission line in the area. The upgrade is assigned partly to this project.
  4. A decision point. The developer must decide whether the project still makes economic sense with that upgrade cost. If it continues, it posts additional security; if not, it withdraws.
  5. Restudy. If other projects in the cluster drop out, the remaining ones may be restudied, and costs can shift up or down.
  6. Agreement and construction. Once costs and schedules are settled, the developer signs an interconnection agreement. The utility then builds the network upgrades while the developer builds the plant.

The project is not truly “in service” until both sides are finished and the facility passes testing. A delay in a single substation component can hold up the whole schedule.

How to Read a Queue Report

Many regional operators publish data on the projects in their queues. Those reports can look overwhelming, but a few fields carry most of the meaning.

  • Status. Phrases such as “active,” “under study,” “agreement executed,” “under construction” and “withdrawn” tell you how far a project has come. Executed agreements and construction are much stronger signals than an initial filing.
  • Fuel or technology type. This shows what kinds of resources are trying to connect, which hints at the future mix of the regional grid.
  • Proposed in-service date. Treat these as targets. They often slip as studies and construction run long.
  • Point of interconnection. Clusters of projects at the same substation or line can signal both opportunity and congestion in that area.

A common mistake

Adding up every megawatt in a queue and calling it the future capacity of a region overstates what is likely to be built. Historically, many requests never reach commercial operation. A more useful view separates projects by stage.

What This Means for Businesses Watching the Build-Out

For companies whose plans depend on new power supply, the queue is a timing tool as much as an engineering process. A few practical takeaways:

  • Announcements about large data center or generation projects are most meaningful when paired with interconnection status.
  • Regions with long queues and heavy upgrade needs may see slower growth, regardless of how much demand exists.
  • Reforms take time to show results. Comparing study timelines across several published cycles is a better test than a single report.

Frequently Asked Questions

Can a project jump ahead in line? Under first-ready approaches, projects that meet readiness requirements, such as demonstrated site control and larger deposits, may move forward more quickly than those that do not. The specific rules depend on the region.

Do batteries go through the same queue? Generally yes, since storage injects power onto the grid. Some regions have special provisions for projects that add equipment at an existing site.

Why don’t operators just build more transmission so studies come back clean? Proactive transmission planning is part of the discussion, but new lines take years and must be paid for by someone, which raises its own cost-allocation questions.

This is general education, not investment advice. Anyone evaluating a specific project or company should consult qualified energy, legal and financial professionals.

Latest stories

View all

Power & Grid

A Maintenance Window Changes the Meaning of Redundancy

A facility’s normal arrangement is only one of its operating states. When equipment is removed from service for maintenance, the remaining paths may carry a different risk. A redundancy label needs to be read with that temporary configuration.

Published

on

Wires connected inside an electrical switch box

Photo: mostafa mahmoudi / Unsplash

A facility's normal arrangement is only one of its operating states. When equipment is removed from service for maintenance, the remaining paths may carry a different risk. A redundancy label needs to be read with that temporary configuration.

The operating distinction

Maintenance can remove a spare component, change a transfer path or increase the load on equipment that remains available. The operational question is which further interruption the system could tolerate in that state. That question may have a different answer from the one given for normal operation.

Advertisement

Temporary states deserve names that operators can recognize. If a system has several possible maintenance configurations, a generic instruction to use the backup can leave too much unstated. The arrangement being discussed should match the equipment actually removed from service.

A practical example

Imagine a hypothetical system with alternate power paths while both are available. During planned work on one path, the other becomes more important. A second task on a related component could create an exposure that neither maintenance activity would create alone.

Questions worth asking

The temporary configuration changes the relevant failure question. Describing the available paths during maintenance helps readers understand both why the work is necessary and which additional conditions the operating team must manage around it.

  • What protection remains while the selected equipment is unavailable?
  • Could another planned activity affect the same remaining support path?
  • What condition would postpone the work or require restoration of the normal arrangement?

What the evidence supports

This does not mean that maintenance should be avoided. Deferred work can increase other risks. It means that timing, dependencies and contingency arrangements belong in the planning discussion. Only qualified personnel following the site's procedures should operate or isolate electrical equipment.

The communication record should also identify when the temporary condition begins and how normal status is restored. Otherwise the next shift may inherit a narrower margin without realizing it. In a public explanation, this can remain high-level: the purpose is to distinguish resilience under normal conditions from resilience during planned work, not to publish sensitive switching instructions or suggest that every maintenance activity creates the same risk.

Advertisement

Describe resilience during the actual maintenance state, rather than borrowing the normal-state label without qualification.

Quick check

How much did you catch? Tap a question to see the answer.

1. Why read a redundancy label alongside maintenance plans?

Answer: Taking equipment out of service changes the risk on the paths that remain.

2. What question matters during maintenance?

Answer: Which further interruption the system could tolerate in that temporary state.

3. Why is “use the backup” too vague?

Answer: It doesn’t say which configuration matches the equipment actually removed from service.

Thinking in Operating States

A helpful habit is to describe a system as a set of named operating states rather than a single design. Each state has its own available paths and its own answer to the question of which further failure it could tolerate. In general terms, a facility might move through states such as these:

  • Normal. All designed paths and spare components are available.
  • Planned maintenance. A specific component or path is intentionally out of service for work.
  • Degraded after a fault. A component has failed unexpectedly and the system is running on the remaining paths.
  • Testing. The system is deliberately placed in a configuration to confirm that a function works.
  • Restoration. Work is complete and the system is returning to normal, but checks are not yet finished.

Describing which state applies, and what remains available in it, gives operators and readers a shared language. It also makes clear that the same facility can have different resilience at different times of the same week.

Planning a Maintenance Window Step by Step

The following outline describes how a planning discussion can be structured. It is not a switching procedure, which belongs to qualified personnel and site-specific methods.

  1. Name the affected equipment and resulting state. State clearly what will be out of service and what the remaining arrangement will be.
  2. Identify what remains protected. Describe which further faults the remaining paths could tolerate.
  3. Check for overlapping work. Review other planned activities, supplier visits and tests that could affect the same remaining path.
  4. Consider external conditions. Weather forecasts, utility notices and unusual load periods may favor a different timing.
  5. Set stop conditions. Agree in advance which developments would pause the work or trigger a return to the normal arrangement.
  6. Communicate the window. Inform affected teams and customers as appropriate, including start, expected end and restoration checks.
  7. Confirm restoration. Verify that normal status has returned and record it so the next shift knows.

Common mistakes

Two unrelated teams scheduling work on components that share a dependency is a classic problem, especially when change records are kept in separate systems. Another mistake is leaving a temporary state in place longer than planned without updating the shift record. A third is treating the restoration as complete as soon as equipment is energized, before checks confirm that the redundant path is genuinely available again.

What This Means for Customers and Readers

For a business hosted in a facility, maintenance notices are an opportunity to understand how resilience changes during planned work. A provider that explains the temporary state, the remaining protection and the stop conditions is communicating useful information. For readers following the industry, a redundancy label describes design intent; operating practice determines how well that intent holds up across the year.

Redundancy is a property of a particular moment, not a permanent label on the building.

Questions Readers Ask

Why not simply avoid maintenance to keep redundancy intact?

Deferred maintenance can increase the chance of unplanned failures. Planned work is usually the safer path when it is scheduled and coordinated carefully.

Can a facility remain fully redundant during maintenance?

Some designs are built to keep a spare path available while one path is under maintenance. Whether that applies depends on the specific design and the work involved.

Should customers be told about maintenance windows?

Many agreements include notification arrangements. The details vary by provider and contract.

What is a stop condition?

A pre-agreed event or reading that pauses the work or triggers restoration of the normal arrangement.

BOSSTOX is coming to iPhone

AI infrastructure explainers and news on iPhone, iPad and Apple Watch.

See BOSSTOX

Continue Reading

Power & Grid

Draw the Outage Boundary Before Comparing Backup Power

A backup-power claim becomes easier to understand when its boundary is drawn on a simple diagram. Keeping a server powered is different from keeping an entire service available, and neither statement describes every possible interruption.

Published

on

Rows of server racks in a data center

Photo: imgix / Unsplash

A backup-power claim becomes easier to understand when its boundary is drawn on a simple diagram. Keeping a server powered is different from keeping an entire service available, and neither statement describes every possible interruption.

The operating distinction

Electricity reaches the application through equipment with different jobs. A battery may support the server while a generator starts, yet the cooling controls, network equipment or building pumps could depend on another circuit. If any necessary part loses power, the application can stop even when its own power supply remains healthy.

Advertisement

The boundary also determines what an availability statement leaves out. A supplier may describe its equipment accurately while a customer reasonably hears a promise about the application. Those interpretations should be reconciled before a purchase or acceptance discussion.

A practical example

Consider a hypothetical hall with battery-backed racks and a cooling pump outside that protected boundary. A short interruption could leave the processors running while coolant circulation stops. The useful question is how the whole service behaves during that interval, rather than whether the rack has a battery.

Questions worth asking

An availability promise becomes clearer when the protected equipment and the promised user outcome are named together. Otherwise different parties can agree on the words while assuming different boundaries around the service.

  • Which supporting systems sit outside the protected power boundary?
  • What happens while the system transfers between power sources?
  • Which test demonstrates the claimed application-level behavior?

What the evidence supports

A drawing is not proof of performance. Actual protection depends on the installed arrangement, controls, maintenance state and tests. Two facilities using the same redundancy label can have different dependencies and different opportunities for a shared failure.

One useful reading exercise is to trace an ordinary user request through the drawing and mark every system it needs. Then consider an interruption at each boundary. This is a discussion exercise, not permission to disconnect equipment. It helps reveal which claims depend on assumptions that have not yet been stated and which supporting systems need evidence of their own before the broader service claim can be understood.

Advertisement

Define the service first, then examine the electrical and mechanical chain that keeps that service running.

Quick check

How much did you catch? Tap a question to see the answer.

1. Is keeping a server powered the same as keeping a service available?

Answer: No. Cooling, networking and building systems can sit on other circuits.

2. What helps make a backup-power claim clear?

Answer: Drawing its boundary on a simple diagram.

3. What can happen if a cooling pump sits outside the protected boundary?

Answer: Processors keep running while coolant circulation stops.

Going Deeper: Drawing the Diagram Step by Step

The exercise described above works best with a plain sheet of paper and a simple method. Here is one way to build the drawing for a hypothetical service before any comparison of backup power begins.

  1. Name the service outcome. Write one sentence at the top describing what users must be able to do, for example “customers can submit and receive answers within the agreed response time.” Everything else on the page exists to support that sentence.
  2. List the systems the request touches. Servers, storage, network switches, firewalls, the cooling loop serving those racks, the controls that run the cooling, and any building systems such as pumps or ventilation that the room depends on.
  3. Mark each system’s power source. Note which ones sit on battery-backed circuits, which rely on generator support only, and which run on ordinary utility power.
  4. Draw the boundary. Circle everything protected by the backup arrangement under discussion. Anything outside the circle is a dependency the claim does not cover.
  5. Walk through the transfer. For each system, ask what happens in the seconds between a utility interruption and the backup source taking over, and again when power returns.
  6. Note the evidence. Beside each system, write what test, document or record shows how it behaves. Blank spaces become the questions to ask.

Why the transfer interval deserves its own line

Batteries and generators do different jobs on different timescales. The battery carries the load immediately; the generator needs time to start and stabilize. Equipment that rides through the first interval may still be affected if it loses support during the second, or if controls reset when the source changes. Writing the sequence down makes those moments visible instead of assumed.

Common Gaps the Diagram Tends to Reveal

  • Cooling controls on a separate circuit. Chillers or pumps may be backed up, but the controllers that tell them what to do might not be.
  • Network equipment outside the protected room. A switch or router in another closet can become the single point that takes the service offline.
  • Shared upstream components. Two “redundant” paths that pass through one panel, one transfer switch or one fuel supply can fail together.
  • Monitoring that depends on the thing it monitors. If alarms run through systems that lose power, operators may not learn of a problem until users do.
  • Restart behavior. Some equipment does not return to normal operation automatically when power is restored and may need manual steps.

Questions to Bring to a Supplier or Facility Conversation

  • Which of the systems on our drawing does your claim cover, and which does it exclude?
  • Is the stated availability measured at the equipment, the room or the service?
  • What recent tests exercised the full transfer sequence, and what did they show?
  • How are maintenance periods handled, when part of the protection may be out of service?
  • Who is responsible for dependencies that sit between your scope and ours?

Questions Readers Ask

Is a redundancy label enough to compare two facilities? As noted above, the same label can describe different arrangements. The drawing and the evidence behind it are what make a comparison meaningful.

Who should draw the diagram? Ideally the people responsible for the service and the people responsible for the facility, together, so that assumptions on both sides end up on the same page.

Does this apply to small server rooms too? Yes. A single rack with a battery unit in an office can still depend on an unprotected air conditioner or network closet, so the same drawing exercise is useful at any scale.

How often should it be updated? Whenever equipment, layout or the service itself changes. A drawing that no longer matches the installed arrangement can be more misleading than none at all.

BOSSTOX is coming to iPhone

AI infrastructure explainers and news on iPhone, iPad and Apple Watch.

See BOSSTOX

Continue Reading

Power & Grid

FERC’s Large-Load Orders: The November 16 Grid Deadline Behind the AI Build-Out

FERC told all six grid operators it regulates to justify or rewrite their rules for connecting data centers and other large loads. After extensions, the answers are due November 16. Here is what to watch.

Published

on

Illustration of high-voltage transmission towers at dusk carrying power lines toward a lit data-center campus.

For most of the AI build-out, the hard question about a new data center has been about hardware: can the operator get the accelerators, the transformers and the cooling equipment? A slower question sits underneath all of them. Who decides how a 300-megawatt customer connects to the transmission grid, how long the study takes, and who pays if the project never arrives?

On June 18, 2026, the Federal Energy Regulatory Commission put that question to every grid operator it regulates. It issued six show cause orders, one each to PJM, MISO, SPP, CAISO, ISO New England and NYISO. Each order tells the operator and its transmission owners to either prove their current rules for large loads are just and reasonable or file new ones. After extensions, the responses are now due on November 16, 2026, for five of the six regions and November 20 for SPP.

This article explains what FERC asked for, where each step stands, and what the filings will tell readers following AI infrastructure.

Advertisement

How the grid got here

Generators that connect to the transmission grid have long had a federal process: a queue, studies and a standard agreement. Large consumers of electricity mostly did not. A new factory or data center usually connected through its local utility under rules set largely by states. That arrangement worked when a large industrial customer meant tens of megawatts. It strains when single campuses ask for hundreds of megawatts, sometimes with their own generation on site.

In October 2025 the Secretary of Energy used his authority under the Department of Energy Organization Act to send FERC an advance notice of proposed rulemaking on large-load interconnection, opened as Docket No. RM26-4-000. FERC says its staff reviewed more than 3,500 pages of public comments. Rather than issue a single national rule, the Commission chose tailored orders under Section 206 of the Federal Power Act, region by region. The rulemaking docket remains open.

FERC staff’s explainer describes the orders as covering facilities with maximum demand of at least 20 megawatts. They build on two earlier actions: a December 2025 order directing PJM to adopt transparent tariff rules for load co-located with generation, and FERC’s approval of SPP’s High Impact Large Load process.

The five issues every region must answer

Each order is tailored to its region, but all six identify the same five areas for reform:

  1. Faster, clearer study processes. A defined application path for large loads with accelerated study timelines, including evaluation of grid-enhancing and alternative transmission technologies.
  2. No cost shifting. Rules that keep upgrade costs for new large loads from landing on other customers, and public transparency into what those upgrades cost.
  3. Co-location and behind-the-meter generation. Clear tariff rules for data centers built next to, or behind the meter of, a power plant.
  4. Services for flexible loads. New transmission products, such as non-firm or contract-demand service, for customers willing to curtail during grid stress.
  5. Studying generation and load together. A process to study new generation alongside the nearby or co-located load it is built to serve.

The second item may matter most for public acceptance. FERC preliminarily found that operators do not publicly post enough data on the upgrades and costs needed to serve new large loads. The remedies it floated include posting each upgrade’s scope, cost and cost assignment, plus a central cost-transparency page on each operator’s website. FERC also asked whether operators should adopt standard cost recovery agreements among the grid operator, the transmission owner and the large customer. Those agreements would protect other ratepayers if a project is canceled or leaves early.

Advertisement

Two limits are easy to miss. The findings are preliminary, and FERC staff note the orders do not impose new transmission rates. The orders also apply going forward. FERC said they are not meant to disturb existing agreements or negotiations already near completion.

Where the clock stands

The orders set two deadlines. Within 30 days, each region had to file an informational report on how it will keep enough generation for existing and new large loads. MISO, for example, filed its report on July 20. Within 60 days, each region had to file its tariff response, unless it asked FERC to pause the case.

The operators asked for that pause, and FERC staff now list November 16 as the response date for five regions and November 20 for SPP. CAISO’s August 3 motion requested a 90-day abeyance so it could build a tailored filing with its transmission owners through an accelerated stakeholder process. MISO and its transmission owners filed a similar request the same day, and MISO reports that FERC granted it on August 14. In MISO’s case, responses are now due November 16 and answers to those responses December 16.

The pause has limits. CAISO’s motion notes that FERC said it would not grant abeyances reflexively. FERC capped them at 90 days and said it would look with great disfavor on requests to extend them further. That makes November 16 a firmer date than regulatory deadlines often are.

Some regional work is moving on a parallel track. CAISO’s published schedule takes its large-load proposal to its Board of Governors on October 28, ahead of the FERC filing. MISO separately filed interconnection reliability requirements for large loads on August 28, asking for a December 4 effective date.

What the filings will reveal

The responses will be long and technical. A handful of questions will say most of what matters about how quickly new AI capacity can connect, and on what terms.

  • Study timelines. Does each region commit to a defined number of days for a large-load study, and what readiness deposits or milestones must a project show to keep its place?
  • Interim service. Can a data center take non-firm or as-available service while network upgrades are built, and how often could that service be curtailed?
  • Financial security. How much must a large customer commit up front, and what happens to that money if the project shrinks or is canceled?
  • Co-location rules. How will regions treat a campus that sits beside a power plant, and what share of grid costs does it carry?
  • Cost posting. Will upgrade costs be published per project, so state regulators and the public can see who pays?

The answers will likely differ by region. A region that offers a fast, well-defined path with clear collateral rules may attract projects that can meet those terms. A region whose answers stay open-ended may keep seeing projects wait in queues and bilateral negotiations. Readers should treat any claimed speed-up with care until the tariff language is approved and the first projects move through it.

The orders also leave a gap. Utilities outside the six RTO and ISO regions, including much of the Southeast and West, are not directly covered. FERC Chairman Laura Swett encouraged those transmission providers to pursue similar reforms through their own filings. ERCOT, which runs most of the Texas grid, is not subject to the orders.

Why this belongs on an AI-infrastructure watch list

BOSSTOX has covered the physical limits on AI capacity: transformer lead times, transmission and local grid upgrades, behind-the-meter generation and on-site storage. The FERC proceeding is the rulebook that ties those pieces together. It decides how a project enters the grid, which upgrades it triggers, and who carries the risk if forecast demand does not arrive.

The dates to watch are concrete: CAISO’s board meeting on October 28, the six responses due November 16 and 20, answers due in mid-December, and the FERC orders that follow. BOSSTOX will review the filings once they are posted and report what each region actually committed to.

This article is general information about a regulatory proceeding. It is not investment, legal or regulatory advice. Filing dates come from FERC and grid-operator documents and may change; check the dockets for the latest.

Sources

  1. FERC, “FERC Launches Aggressive Targeted Action to Speed Large Load Integration,” June 18, 2026: ferc.gov
  2. FERC Office of Public Participation, “Cost Transparency and Customer Protection Initiatives in FERC’s June 2026 Show Cause Orders for Large Load Interconnections”: ferc.gov
  3. California ISO, “Motion for Abeyance,” Docket No. EL26-71-000, August 3, 2026: caiso.com
  4. MISO, “Large Load Working Group FERC Status Report,” September 9, 2026: misoenergy.org
  5. Akin Gump, “FERC Issues Landmark Show Cause Orders on Large Load Interconnection,” June 2026: akingump.com